2532/K
IN THE MATTER OF AN AD HOC ARBITRATION
BETWEEN
CANADIAN NATIONAL RAILWAY COMPANY
(“the Company” / “CN” / “the Employer”)
- AND -
UNIFOR LOCAL 100
(“the Union”)
CONCERNING THE SHOPCRAFT GRIEVANCE of PR0120
SHP-748
Pursuant to the parties’ Video Conference Arbitration Handling Guidelines of June
15, 2021
Christopher Albertyn - Sole Arbitrator
APPEARANCES
For the Union:
Joel Kennedy (Presenting), National Rail Director
Cory Will, President, Unifor Local 100
Jason Lancaster, Prairie Region Vice President, Unifor Local 100
For the Company:
Richard Charney, Senior Partner, Norton Rose Fulbright
Samual Keen, Associate, Norton Rose Fulbright
Mark Grubbs Sr, Vice-President Mechanical, CN
Melanie Martens, Director LR & HR Compliance, CN
Ron Campbell, Labour Relations Manager, CN
Hearing held by videoconference on July 29, 2024.
Award issued on October 15, 2024.
1
AWARD
1. This award concerns shopcraft grievance PR 120 of May 21, 2020.
2. The parties’ Joint Statement of Issue reads as follows.
JOINT STATEMENT OF ISSUE
Dispute
Contracting out work presently and normally performed by Unifor
bargaining unit members working at the Traction Motor Shop, Air
Brake Shop, and Wheel Shop at Canadian National Railway’s
Transcona Shops.
Joint Statement of Issue
On May 11, 2020, the Company notified the Union of its decision to
temporarily close the Traction Motor Shop, Air Brake Shop and
Wheel Shop, due to “the cataclysmic effect of the pandemic on our
business and on our customers, and as a result train starts were
curtailed, locomotives and cars were stored, and consumption of
wheel and other parts decreased proportionally”. These shops have not
been reopened.
On May 21, 2020, the Union filed a Step II grievance alleging the
Company had contracted out work, and that it had done so without
providing any notice (the “Grievance”).
On October 29, 2020, the Company responded, declining the Union’s
2
grievance.
3. The dispute concerns the application of Rule 51, Contracting Out.
RULE 51
Contracting Out
51.1 Work presently and normally performed by employees who are subject
to the provisions of this collective agreement will not be contracted out
except:
(a) when technical or managerial skills are not available within the
railway; or
(b) where sufficient employees, qualified to perform the work, are not
available from the active or laid-off employees; or
(c) when essential equipment or facilities are not available and cannot
be made available at the time and place required (a) from Railway
owned property, or (b) which may be bona fide leased from other
sources at a reasonable cost without the operator; or
(d) where the nature or volume of work is such that it does not justify
the capital or operating expenditure involved; or
(e) the required time of completion of the work cannot be met with the
skills, personnel, or equipment available on the property; or
3
(f) where the nature or volume of the work is such that undesirable
fluctuations in employment would automatically result.
The conditions set forth above will not apply in emergencies, to items
normally obtained from manufacturers or suppliers nor to the
performance of warranty work.
51.2 The Company will advise Union representatives in writing, as far in
advance as practicable, but no less than thirty days except in cases of
emergency, of its plans to contract out work which would have a
material and adverse effect on the employees.
In all instances of contracting out, the Company will hold discussions
with the representative of the Union in advance of the date contracting
out is contemplated, except in cases where time constraints and
circumstances prevent it.
To this end, at mutually convenient times on a quarterly basis, the
National President of Local 100, the Local 100 Vice Presidents and the
Unifor National Representative (or designates) and the appropriate
company officers (Chief Mechanical Officers or designates) will meet
to discuss the Corporation's plans with respect to contracting out of
work for the coming months.
51.3 The Company will provide the Union with a description of the work to
be contracted out; the anticipated duration; the reasons for contracting
out, and, if possible, the approximate date each contract is to
commence, and any other details as may be pertinent to the Company’s
decision to contract out. During such discussions, the Company will
4
give due opportunity and consideration to the Union’s comments on the
Company’s plans to contract out and review in good faith such
comments or alternatives put forth by the Union. If the Union can
demonstrate that the work can be performed internally in a timely
fashion as efficiently, as economically, and with the same quality as by
contract, the work will be brought back in or will not be contracted out,
as the case may be. Where a business case cannot be made to have the
work performed by Unifor members under existing collective
agreement terms and conditions, the parties may, by mutual agreement,
modify such terms and conditions in an effort to have the work
performed by Unifor members.
51.4 Should a Regional Vice-President, or equivalent, request information
respecting contracting out which has not been covered by a notice of
intent or discussed in a quarterly meeting, it will be supplied promptly.
If the Regional Vice-president requests an additional meeting to discuss
such cases of contracting out, it will be arranged at a mutually
acceptable time and place.
51.5 Where the Union contends that the Company has contracted out work
contrary to the provisions of this Rule, the Union may progress a
grievance by using the grievance procedure which would apply if this
were a grievance at step 2 under the Collective Agreement. The union
officer shall submit the facts on which the Union relies to support its
contention. Such grievances will be submitted directly to the
appropriate company officer (Chief Mechanical Officer or department
Director), with a copy to Labour Relations, and will be discussed in
joint conference or as part of the next scheduled quarterly meeting. Any
such grievance must be submitted within 30 days from the alleged non-
5
compliance, failing which the matter shall be deemed to be closed.
Facts
4. In about May 2020, at the early peak in the COVID-19 pandemic, the
Company decided to close the Transcona Shops (“the shops”) in Winnipeg (the
Wheel Shop, the Air Brake Shop and the Traction Motor Shop). This decision was
made because the railway had much reduced mileage and had built a surplus stock
of wheels and other parts that it could use. The Union accepts that this initial
decision to shut down the shops was legitimate.
5. The Union’s concern is with the Company’s decision to keep the shops
closed once the surplus stock of wheels and other parts had been used up, and the
Company’s refusal to resume production at the Transcona Shops. Instead, it
transferred the work to third-party contractors. That is what the Union objects to.
6. CN has not reopened the shops, and it has no plans to do so. Instead, CN
expanded its use of third-party contractors. The grievance concerns these decisions,
and it concerns the way in which the Company failed to engage with the Union to
effect the contracting-out and to maintain the shuttering of the shops.
7. The history of this matter starts in 2010. That is the start date of the details
the Company has provided of the scope of its contracting-out of the work of the
Transcona shops. From 1998 until 2001 there were derailments from improperly
modified wheel boring, principally from the Wheel Shop. The wheelsets were loose
and could cause car derailments. CN identified that the defects were being caused
by the Wheel Shop equipment that had become outdated and needed replacement.
So, in 2010, the Company undertook a review of the potential cost of renovating
and upgrading the Wheel Shop. The quote it received (“the Simmons Proposal”)
estimated it would cost between $19 and $25 million to replace the existing
6
equipment. This potential cost was prohibitive, and CN decided not to proceed with
the contemplated improvements in the equipment.
8. CN did not engage the Union at all on the above considerations. As a result,
the Union was unaware of the contemplated refurbishment, of the potential costs of
doing so, and of the decision not to proceed with the necessary improvements. This
meant that the Union did not have any opportunity to provide input on how the
situation could be addressed. CN let the equipment in the Wheel Shop run down
because the cost of improving it was prohibitive.
9. The contracting-out of the work of the Transcona Shops started in 2003.
From 2010 the percentage of the contracted-out work of the three shops (Wheel
Shop, Air Brake Shop, Traction Motor Shop) was as follows, with subsequent
changes:
Wheel Shop contracted-out work:
2010: 23%
2019: (just before the pandemic and the notice of closure): 79%
2023: 93%
Traction Motor Shop contracted-out work:
2010: 30%
2019: 70%
2020: 100%
Air Brake Shop:
Valves 22-23-506 contracted-out work:
2010: 72%
2019: 60%
2020: 100%
Valves 22-24-508 contracted-out work:
2010: 49%
2019: 58%
2020: 100%.
7
10. From the above, the result of the closure of the shops in 2020 was that a
very small portion of the Wheel Shop was retained, but 93% was contracted-out,
and all the work of the Traction Motor Shop and of the Air Brake Shop was
contracted-out.
11. The Union claims that it was unaware of the above contracting out until the
information was disclosed in this matter and says that it never had an opportunity
to address the issue. However, there were two previous grievances concerning
contracting out. The first in 2014, which was withdrawn; and in 2018 which was
resolved without prejudice. I have no further information on these grievances nor
on the resolution of the second.
12. Prior to the closure of the shops in May 2020, the Company conducted a
financial analysis of the cost differences between doing the work in the Wheel Shop
as compared to having the work done by third-party contractors. The analysis
revealed that CN could have saved over $3.8 million in 2019 if all the work were
done by contractors. Similarly, it would have saved $336,550 by moving the work
at the air break shop to third-party service providers. In total, the 2019 financial
analysis estimated it would have saved over $4.5m in 2019 had it given the work
of the Transcona Shops to third-party contractors.
13. The impact of the shuttering of the shops in 2020 was that the following
positions were eliminated:
- 3 jobs in the Air Brake Shop
- 11 jobs in the Traction Motor Shop
- 30 jobs in the Wheel Shop.
14. The Union learned of the closing of the shops on May 11, 2020. The
8
employees affected by the closure were told the next day, May 12, 2020, that their
jobs were to be eliminated on May 15, 2020 (three days later).
15. 63 employees were affected by the closure. 40 were absorbed into other jobs
in the Transcona Shops; 23 were laid-off, but, by February 2021, all who wished to
return were recalled to work. The affected employees were mostly absorbed into
locomotive maintenance.
16. There was no discussion with the Union by the Company prior to the shop
closures in May 2020. There was also no information supplied to the Union in the
period following, despite repeated requests by the Union to be told of CN’s
intentions, particularly as to when it would re-open the shops, and as to the extent
of the contracting-out it was doing.
17. The Union filed this grievance on May 21, 2020, when it received no initial
information from the Company.
18. The first substantive response to the Union was on October 29, 2020,
denying the grievance. CN’s reply explained that the shutdown had been necessary
in May 2020 because of the surplus stock built up through the pandemic. CN denied
that it had contracted-out more work than prior to the downturn in traffic. No
information was given as to the Company’s future intention.
19. On the same date, October 29, 2020, the Union referred the grievance to
arbitration.
20. The figures provided by the Company for this case, indicating the
significant increase in the percentage of work contracted-out in 2020, do not accord
with the statement made on October 29, 2020 that the Company had not, by the
time of that reply, contracted out a much higher percentage of the overall work of
9
the shops than it had prior to the pandemic. The information it gave to the Union
was therefore false.
21. The date of hearing of the arbitration was scheduled before me on October
18, 2022. Shortly before that date, in September 2022, CN requested a meeting with
the Union. By then the contracting out was complete.
22. The parties met on September 9, 2022 and they discussed the grievance.
They concluded a Memorandum of Settlement. In it the Company agreed to assess
the viability of reopening the shops “based on the cost of upgrading existing
equipment and processes to appropriate safety standards with a view of exploring
options for modernizing the shop”. The parties agreed to work collaboratively on
safety recommendations. The Company agreed to provide the Union with regular
bi-monthly updates on the progress of the assessments of the Wheel Shop. In return,
the Union agreed to hold the grievance in abeyance for six months. I was advised
that the hearing scheduled for October 18, 2022 was cancelled.
23. The parties further agreed that, at the conclusion of the six-month
assessment period, they would meet to discuss the Company’s plans regarding the
possible re-opening of the Wheel Shop. The Union could proceed with the
arbitration if the outcome of the assessment was unsatisfactory.
24. Pursuant to the obligation the Company undertook in the Memorandum of
Settlement, CN commissioned NSH USA, Simmons’ successor, to prepare two
proposals for a new Wheel Shop at Transcona: one that would be fully automatic,
the other semi-automatic.
25. NSH’s proposals for the two alternatives was received by the Company on
August 15, 2023. For the automatic Wheel Shop, the cost of refurbishment would
be over $42.7 million. CN anticipated it would incur a further $14.6m in civil
10
engineering expenses to build a new Wheel Shop at Transcona. In total, CN
estimated that building a fully automatic Wheel Shop would cost approximately
$65 million. Such a shop would require only 36 employees.
26. For the semi-automatic Wheel Shop, the estimated total cost would be $54.5
million, with relatively few employees.
27. The Company concluded that that the cost of modernizing and reopening
the Wheel Shop was not financially viable. It advised the Union of this, and the
Union revived the arbitration.
Analysis
28. CN denies it violated the collective agreement by closing the Transcona
Shops. Alternatively, if there was contracting out, the Company submits it complied
with its obligations under Rule 51. Further alternatively, CN claims, if there was a
breach it was merely technical in nature and no remedy is appropriate.
29. CN’s argument is that it did not contract-out the work because the work was
given to the third-party contractors in an emergency, for sound operational reasons,
and in good faith.
30. There is no factual foundation for this argument. As can be seen from the
figures provided above, work “presently and normally performed by employees
who are subject to the provisions of this collective agreement” has steadily been
contracted-out by the Company, starting in 2003 and increasing proportionately
from 2010. Nonetheless, a substantial portion of the overall work continued to be
done at the Transcona shops until the COVID-19 pandemic shutdown in 2020.
31. Following the initial emergency shutdown in 2020, there was a substantial
11
increase in contracted-out the work “presently and normally performed by
employees” (see AH-453). Such contracting out is, prima facie, a breach of the
Company’s obligation not to contract-out the bargaining unit work.
32. CN argues that, to the extent work was contracted-out, that was permissible
under Rule 51(d), which allows for contracting out when the capital and operating
expenditures necessary to keep work within the bargaining unit cannot be justified
in light of the nature and volume of the work involved.
33. What is not quite apparent from the facts is whether the Company needed
to contract-out the bargaining unit work. The Company alleges that the Wheel Shop
at Transcona had reached the end of its lifespan. However there is insufficient
evidence that the Wheel Shop was in such a state of disrepair that it could no longer
do the wheel work required of it. It certainly seems that a refurbished shop would
perform better, but there was no indication to the Union during the period leading
to the pandemic that the Wheel Shop’s lifespan was ending. It is therefore unclear
that it was a necessity to close down the Wheel Shop and the other Transcona Shops
after the surplus product had been used up in the early part of the pandemic in 2020.
34. It was certainly better for business because the work could be done at a
cheaper price by external contractors. But there is little to suggest that the Company
could not have reopened the Transcona shops and continued operating as it did in
2019, with the same proportion of the work done at the shops and by third-party
contractors. At some point it would become clear that the Wheel Shop would have
to be substantively refurbished, but it is not evident from the information provided
thus far that that was a necessity when the decision was made to keep it closed.
35. The Union claims that the first time the issue of the alleged end-of-life of
the Wheel Shop was raised by the Company was in CN’s submissions for this
12
arbitration. That issue was not discussed with the Union prior to the Company’s
decision to shutter the Wheel Shop. However, it was presumably discussed in the
conversation between the parties on September 9, 2022, when the Memorandum of
Settlement was concluded. That is because the Memorandum of Settlement had the
parties agreeing to assess the possibility of reopening the Transcona shops “based
on the cost of upgrading existing equipment and processes to appropriate safety
standards with a view of exploring options for modernizing the shop”. The Union
now takes the position that the Wheel Shop can continue to be fully functional and
that the contracted-out work can return to it.
36. The Union argues that the Company has destroyed the core work of the
bargaining unit – the refurbishing of the wheels – by contracting it out and not
having it done at Transcona. The Union argues this constitutes a permanent loss of
bargaining unit work, without justification.
37. When making the decision to contract-out work, the Company had certain
obligations under Rule 51.
38. Firstly, under Rule 51.2, it must “advise Union representatives in writing,
as far in advance as practicable, but no less than thirty days except in cases of
emergency, of its plans to contract out work which would have a material and
adverse effect on the employees”.
39. The Union accepts that the circumstances causing the sudden closure of the
shops in May 2020 was an emergency. It has no complaint against the Company
for acting as it did then. The Company had to adjust to the sudden drop in demand
occasioned by the pandemic, in circumstances when it had an immediate surplus of
replacement wheels and parts.
40. What the Union does complain of, with justification, is the decision not to
13
re-open the shops once the surplus product had been used up. It was then that the
Company decided to expand its contracting out of work previously done by
bargaining unit employees.
41. That decision required the Company to comply with Rule 51.2. The
emergency had passed then. The full obligation existed, and it was not complied
with. There was no notice in writing, never mind a notice, “as far in advance as
practicable”. The decision was made and acted on without any involvement of the
Union. That was plainly a breach of Rule 51.2.
42. Rule 51.2 continues: “In all instances of contracting out, the Company will
hold discussions with the representative of the Union in advance of the date
contracting out is contemplated, except in cases where time constraints and
circumstances prevent it.”
43. There were no time constraints for the decision to expand the contracting
out during 2020. The Company was obliged to hold discussions with Union
representatives before implementing the decision to expand the contracting out.
That did not happen. That was a further breach of Rule 51.2.
44. Rule 51.3 was similarly breached. That Rule requires the Company to give
a description of the work to be contracted-out, with details of the anticipated
duration, with reasons for doing so, with the approximate date when the contracting
out would occur, and other pertinent details. None of that was provided.
45. The purposes of Rule 51.2 and Rule 51.3 are to give the Union an
opportunity to make representations and to explore alternatives to contracting out
with the Company. That opportunity was denied. The purpose of Rule 51 was
therefore thwarted by the Company’s failure to engage at all with the Union on the
decision to permanently contract-out the work.
14
46. The purpose is stated in Rule 51.3: to give the Union the opportunity to
“demonstrate that the work can be performed internally in a timely fashion as
efficiently, as economically, and with the same quality as by contract”. If the Union
can do that, then the work “will be brought back in or will not be contracted-out”.
By failing to engage the Union, that opportunity was eliminated. There was,
therefore, a violation of Rule 51.3.
47. Rule 51.4 gives the Regional Vice-President of the Union the entitlement to
request information on the contracting out. That information must be supplied
promptly. The Union made numerous attempts to obtain information on what was
happening, on when the work would recommence, on what contracting out was
being done, on what the Company’s intentions were. All of those requests were met
with silence until the Company finally engaged with the Union within a month of
the arbitration hearing date, approximately a year later, in September 2022. That
was a considerable period of time during which the Company neglected the Union
and ignored its rights under Rule 51.4. That Rule was also plainly breached. The
situation was as described by Arbitrator Hornung, at para. 42 of AH-701, “the
failure of the Company to a provide the required information adversely affected
[the Union’s] ability to represent its members and compromised its ability to assess
its position relative to the contracting out of the work at issue”.
48. In presenting the economic justification for the contracting out, the
Employer claims that Rule 51.1(d) applies: it may contract-out work “where the
nature or volume of work is such that it does not justify the capital or operating
expenditure involved”. There has clearly been a significant saving in the operating
expenditure involved by contracting out the work of the shops. There is also a
significant saving by not having to incur the capital costs of transforming the Wheel
Shop. The Company claims that the lifespan of the machine shop and other shops
15
was coming to an end and the expensive refurbishment had to be faced. In
argument, CN suggested that to re-open the shops, after they were closed in 2020,
would have required the expenditure of $55-$65 million. The Union disputes this
assessment, claiming there was no need to keep the shops shut once the excess stock
had been used.
49. There has not yet been any serious engagement between the parties
regarding the Company’s justification for the contracting out. That needs to occur
in a genuine discussion of alternatives by the parties, as is contemplated in Rule
51.2. This is particularly the case when an employer has contracted out the core
work of the bargaining unit, apparently on a permanent basis, so eroding the
Union’s bargaining unit (see SHP-575).
50. The seriousness of the various breaches of Rule 51 is such that a mere
declaration is not sufficient remedy for the Union (see SHP-575 and SHP-715). To
merely make a declaration with nothing further would effectively ignore, and
thereby undermine, the agreement of the parties in Rule 51. Further consequences
should flow from the brazen disregard of the Union’s rights.
51. The Union refers to the award of Arbitrator M. Picher in SHP-409. There
the arbitrator found that there was no justification for the contracting out of the
bargaining unit and he ordered the Company to cease the contracting out of the
bargaining unit work and to return that work to the bargaining unit. Further, there
was an order that all affected employees be compensated for all wages and benefits
lost, and the Union be compensated for any related union dues lost.
52. Arbitrator Picher’s decision in CROA-1596 is similar. There the employer
had no justification for the contracting out of the work other than saving on
operational expenses. The award makes clear that contracting out is not permitted
merely because to do so would be more profitable. Relying on CROA-713, the
16
arbitrator said that contracting out is justified on economic grounds only in
circumstances “where some new or occasional venture is contemplated which
require, if the employer’s own forces were used, some capital or operating
expenditure beyond those of the existing operations and which would not be
justified for the venture contemplated”.
53. CN’s explanation for the contracting out is because of the financial savings.
SHP-409, CROA-713 and CROA-1596 would suggest that this explanation may be
insufficient to justify contracting out of bargaining unit work. CN’s further
justification is that the cost of refurbishing the machine shop would be prohibitively
expensive, as has been explained. That explanation, if genuinely the reason for not
re-opening the Transcona shops, could justify the contracting out, in light of
Arbitrator M. Picher’s finding in CROA-2869. There he found that the large capital
or operating expenditure required to reopen a facility justified keeping it closed. A
similar finding was made in SHP-117.
54. The Company considered the cost of refurbishing the machine shop in 2010.
It was prohibitively expensive then. The Company’s most recent investigation –
with the cooperation of the Union – has revealed that the expense would be even
more prohibitive now.
55. As I have said, what is not apparent is what the remaining life of the shops
would be had they not been shuttered by the Company in 2020, and what other
alternatives could be considered. More information is needed before a clear
conclusion can be drawn on that issue. If it is clear that the closed shops can
continue to operate effectively without the very substantive expenditure in
refurbishing them, then their re-opening is a possible order to be made. If that is not
the case, and the need for the refurbishment is such that “it does not justify the
capital or operating expenditure involved”, then the remedies will need to be
17
different, to address the Employer’s flagrant breaches of Rule 51.
56. In all of the above circumstances, as was done in SHP-741, this award will
make a finding of a breach of Rule 51 – which are substantive, and not merely
technical – and it will direct the parties to meet to consider the appropriate remedies.
As part of the conversation to resolve the issue of remedy, the parties must have a
genuine discussion regarding the need and implications of the contracting out of
bargaining unit work. The parties must jointly explore any alternatives to
contracting out, including remedies for lost work.
57. If the parties are unsuccessful, I remain seized to deal with the remedies.
Award
58. I declare that the Company has violated Rule 51 in each of the ways
described above.
59. I refer the additional remedies back to the parties.
60. To enable the Union to make an informed submission on remedy, and to
engage properly in the attempted resolution of the remedy, the Company is directed
to disclose all relevant information not already provided:
a. of the scope and nature of the contracted-out work;
b. pertinent to the Company’s claim that the state of the Transcona shops
is such that the Company can no longer resume the bargaining unit
work performed there until the shutdown in 2020, without incurring the
substantial refurbishing costs described above;
18
c. of any Company proposals to address the question of the appropriate
remedy.
61. The Company must hold itself reasonably available for the purpose of such
engagement with the Union.
62. If the parties are unable to resolve the remedy, a further hearing will be held
to determine what remedies are appropriate.
DATED at TORONTO on October 15, 2024.
_____________________
Christopher J. Albertyn
Arbitrator